Construction on the new auxiliary gym at Lapeer West High School has been moved up a week requiring the closing of half the existing north parking lot to begin a week earlier on April 14th.
Starting on April 14, student pick-up and drop-off by parents will be in the south lot only, or in front of the high school before school and after the buses depart at 2:15 p.m.
All students who drive to school must park in the south lot.
Some teachers may also have to park in the south lot due to the reduction in spaces in the north lot after it is sectioned in half.
The change is necessary to create a contractor-only entrance from the north lot to the new construction site. A temporary road will be built behind the West portables to allow for contractor traffic to the work site.
Thanks to everyone for their cooperation in this matter.